SHE Onsite home

SWMS or JSA? What New Zealand businesses use instead

Updated

A SWMS (safe work method statement) is an Australian document that the law there requires before high risk construction work. New Zealand law has no SWMS requirement. Here, crews usually plan risky tasks with a job safety analysis (JSA) or a task analysis, and write a SWMS only when a client asks for one by that name.

What is a SWMS in Australia?

In Australia, a SWMS is a legal document under each state's workplace safety regulations. SafeWork SA says businesses, "including self-employed persons, must prepare a safe work method statement (SWMS) before commencing high risk construction work (HRCW)" (SafeWork SA).

There are 18 kinds of high risk construction work. They include work with "a risk of a person falling more than 2 metres", work "in or near a shaft or trench with an excavated depth greater than 1.5 metres", work near energised electrical installations, work that may disturb asbestos, and work in areas with moving powered mobile plant.

The Australian SWMS must, at a minimum, identify the high risk work, state its hazards and risks, set out the controls and how they'll be put in place, and be easy for workers to understand.

Does New Zealand law require a SWMS?

No. New Zealand works under the Health and Safety at Work Act 2015 (HSWA), not Australia's WHS laws. HSWA doesn't name a SWMS, a JSA or a task analysis. It puts duties on the business instead, mainly the primary duty in section 36 to ensure "so far as is reasonably practicable" the health and safety of workers and others affected by the work.

How you show you've planned a risky task is up to you, unless a client's contract says otherwise. New Zealand does have its own legal notices for some work. For example, WorkSafe needs 24 hours' notice of particular hazardous work, such as some trenches over 1.5 metres deep.

What do New Zealand businesses use instead?

The names vary, but they all do the same job: break a task into steps, list what could hurt someone at each step, and say how you'll keep people safe.

NameWhere you'll see itWhat it usually looks like
Job safety analysis (JSA)Common across NZ trades and civil workA table of job steps, hazards and controls, signed by the crew
Task analysis (TA)Common in NZ constructionMuch the same as a JSA, sometimes with a risk rating for each step
Safe work method statement (SWMS)When a client, or a business with Australian links, asks for itA JSA-style plan for a high-risk task, often with more detail on method and equipment
Safe work plan or job safety planSome principals and councilsAn umbrella name that can mean any of the above

WorkSafe New Zealand publishes its own JSA template, with space for each job step, the hazards, the controls, and the names and signatures of the crew who agree to them.

The Ministry of Education's SSSP checklist is a good example of how NZ clients use the terms. It asks for safe work methods for critical or high-risk work through "A task analysis (T/A). Safe works method statement (SWMS) or Job Safety analysis (JSA)". Any of the three is accepted.

Why do people in NZ search for "SWMS"?

A few reasons:

  • Templates. Many free templates online are Australian, so the word turns up in search results.
  • Clients. Some NZ principals and councils use "SWMS" in their tender documents.
  • Crews that work both sides of the Tasman. A business that works in Australia needs real SWMSs there.
  • Habit. People who learned the trade in Australia bring the term with them.

If an Australian template is all you have, change it before you use it in New Zealand. Swap references to the WHS Act and Regulations for HSWA, and take out Australian rules such as the 2 metre fall trigger, which isn't New Zealand law.

What if a client asks for a SWMS?

Give them what they ask for, by the name they use. A good JSA usually has everything a SWMS needs. Check the client's requirements for extra parts, such as:

  • the equipment and plant you'll use, and their checks
  • the tickets and licences the crew need
  • permits, such as for hot work or confined spaces
  • the emergency plan for that task

Then have the crew read it and sign on, and keep the signed copy.

What makes a good JSA or SWMS?

  • Written for this job on this site. A plan copied from last month's job misses what's different this time.
  • Steps in the order they happen. Most people find hazards by walking through the job in their head.
  • Real controls. "Be careful" isn't a control. "Edge protection on every open edge before work starts" is.
  • Strongest controls first. Remove the hazard if you can, then swap it for something safer, then guard or separate it, then use procedures, and PPE last.
  • Signed by the people doing the work. If someone can't read it, go through it with them in person and note that you did.
  • Changed when the job changes. New conditions mean a new version, and the crew sign on again.

This is general information. Check it fits your work. It is not advice.

Next step: see how crews sign on to JSAs on their phones in SHE Onsite's toolbox talks, JSAs and checks, get our free JSA template, or compare plans.

Start your 30-day free trial